01 Purpose

Operate Β· inspect Β· record Β· verify

Handover is an operating test, not a photoshoot.

A snag is something that still needs correction, completion, adjustment or repair before final acceptance.

A door rubbing against the floor, a socket that does not work, an unfinished paint patch, a drawer collision, poor shower drainage or a window that does not lock properly are all snags.

Rule If it moves, move it. If it operates, operate it.
Educational architectural illustration showing snagging should proceed room by room using a repeatable checklist rather than memory
Inspect systematically ↓

02 Inspect

Go room by room, then test each system.

Do not try to remember the whole house at once. Follow a systematic route through living areas, bedrooms, bathrooms, kitchens, utility areas, balconies and terraces.

Educational architectural illustration showing doors and windows must be opened, closed, locked and checked for alignment rather than judged only by appearance
Doors & windows

Operate everything

Open, close and lock them. Check movement, hinges, latches, handles, floor clearance, alignment, seals, glass and frame damage.

Floors & walls

Inspect the finish

Look for cracks, chips, stains, uneven joints, damaged skirting, awkward cuts, unfinished patches, damp marks and poor edge work.

Bathrooms & electrical

Use the systems

Run water and test drainage, leaks and flow. Operate lights, fans, regulators, dimmers, sockets and installed controls.

Joinery

Move every part

Open drawers, wardrobes, cabinets and shutters. Check rubbing, loose hinges, alignment, finishes, hardware and soft-close functions where included.

Record the defects ↓

03 Record

A useful snag list is precise enough to act on.

Do not write something vague such as β€œBathroom issue.” Record the room, exact location, problem, photograph and date.

For example: β€œMaster Bathroom – Shower Area – water remains beside door after shower test.” That gives the contractor a specific item to inspect and close.

Every snag should remain open until it has been corrected and verified. Completed items should be marked closed rather than deleted so that the project retains a record.

Educational architectural illustration showing snagging checks physical performance across floors, walls, ceilings, bathrooms, electrical points and joinery
Educational architectural illustration showing every snag should have a precise location, evidence, responsible party, status and verification before closure
Before closing a snag
Was the correction actually retested?
  • Record the room and exact location.
  • Describe the fault clearly.
  • Photograph the issue where useful.
  • Record the date.
  • Assign and correct the problem.
  • Retest the repaired item.
  • Mark it closed only after verification.
Test the process ↓

04 Check

Snagging is an operating test.

A component can look perfectly aligned and still fail in use. Appearance alone is not enough to close the inspection.

Remember Handover is an operating test, not a photoshoot.
A drawer looks perfectly aligned. What should you do?

Choose the action that verifies actual performance.